Price List Update Summary - December 2021
New Xactimate Line Items
Looking for more helpful Xactimate estimating information? Check out the Commonly Overlooked Line Items database of Xactimate line items that are often warranted but rarely included in invoices/estimates!
COMMONLY OVERLOOKED LINE ITEMSDecember 2021 Price List Changes Report
December 2021 Price List Changes Report
Price list items added for the December 2021 price lists
Batt insulation replacement per LF – 4" – up to 4′ tall
Included: Batt insulation, staples, and installation labor.
Quality: 4" deep with paper or foil facing.
Notes: Generally used in 2" x 4" walls.
Batt insulation replacement per LF – 6" – up to 4′ tall
Included: Batt insulation, staples, and installation labor.
Quality: 6" deep with paper or foil facing.
Notes: Generally used in 2" x 6" walls.
Generator temporary power cable ramp (per day)
Included: Daily equipment cost for a generator power cable ramp/protector.
Quality: 3′ section, up to 5 cable channels.
Notes: To be used in conjunction with a temporary power generator, if needed.
Generator temporary power cable ramp (per week)
Included: Weekly equipment cost for a generator power cable ramp/protector.
Quality: 3′ section, up to 5 cable channels.
Notes: To be used in conjunction with a temporary power generator, if needed.
Power distribution box – 100+ amp (per day)
Included: Daily equipment cost for a generator panel box.
(100 amp and greater). Meets OSHA standards for temporary power connections on a job-site.
Power distribution box – 100+ amp (per week)
Included: Weekly equipment cost for a generator panel box.
(100 amp and greater). Meets OSHA standards for temporary power connections on a job-site.
Add on to tear out mortar bed for tile
Add on to tear out floor drain – tub/shower- metal/plastic
Add on to tear our tile concrete shower curb – per LF
Add on to tear out tile framed shower curb – per LF
Add on to tear out shower drain-for use w/ wtrprf membrane
Tear out non-salv. tile & bag for disposal
Included: Plastic bags and labor.
Tear out non-salv. tile & bag for disposal – after hours
Included: Plastic bags and labor.
Tear out non-salvageable tile, no bagging
Included: Labor cost to remove non-salvageable tile and to discard in a job-site waste receptacle.
Tear out non-salv. tile, no bagging – after hours
Included: Labor cost to remove non-salvageable tile and to discard in a job-site waste receptacle.
Notes: A premium charge is used after normal business hours.
Tear out non-salv. tile & bag – Category 3 water
Included: Plastic bags and labor.
Reference: IICRC S500 5th Edition standards.
Tear out non-salv. tile & bag – Cat 3 water – after hours
Included: Plastic bags and labor.
Reference: IICRC S500 5th Edition standards.
Tear out non-salv. tile, no bagging – Category 3 water
Included: Labor cost to remove non-salvageable tile and to discard in a job-site waste receptacle.
Reference: IICRC S500 5th Edition standards.
Notes: A premium charge is used when working with sewage contaminated materials.
Tear out non-salv. tile, no bagging – Cat 3 – after hours
Included: Labor cost to remove non-salvageable tile and to discard in a job-site waste receptacle.
Reference: IICRC S500 5th Edition standards.
Price list items modified for the December 2021 price lists
- FRMFRHNG* Added text to Quality field of (+) definition to reference framing hanger size ranges.
- INSBTLF4 Modified material component yield in (+) assembly.
- INSBTLF6 Modified material component yield in (+) assembly.
- PNTFAUX* Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTFHF* Modified Included field of (+) definition to clarify labor for covering all sides of the doors would be included.
- PNTLOWF* Modified Included field of (+) definition to clarify labor for covering all sides of the doors would be included.
- PNTP Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTP+ Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTP2* Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTS Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTS- Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTS+* Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTS2 Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTS3 Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTSP Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTSP+ Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTSP2* Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTSPMP Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTSPSB* Modified Note field of (+) definition to further clarify what assumptions are included in the price.
- PNTUPF* Modified Included field of (+) definition to clarify labor for covering all sides of the doors would be included.
- PNTVANF* Modified Included field of (+) definition to clarify labor for covering all sides of the doors would be included.
- STR4C Modified Included field of (+) definition to reference 1" x 8" risers.
- STR6C Modified Included field of (+) definition to reference 1" x 8" risers.
- TMPGENC* Modified Quality and Note fields of (+) definition to reference item is intended to be used for various cable types.
- TMPGENPB* Modified Quality field of (+) definition to reference “below 100 amp."
- WTRDRY Modified Quality field of (+) definition to reference air movers greater than 950 CFM.
- WTRDRY- Modified Quality field of (+) definition to reference mini air movers less than 950 CFM.
- WTRPOWD* Modified Quality field of (+) definition to reference “below 100 amp.
Equipment components added for the December 2021 price lists
- ELEPOWD> Power distribution box – 100 amp or greater
- ELEPOWDW> Power distribution box – 100 amp or greater – per week
- TMPGENCR Temporary power cable ramp/protector 3′ section – per day
- TMPGENCRW Temporary power cable ramp/protector 3′ section – per week
Miscellaneous changes made for the December 2021 price lists
- Updated the Worker Wage portion of the Retail Labor Rates for various areas in the United States and Canada.
- Modified Reference field of item definitions to reference “IICRC S500 5th Editions standards” where applicable.
Future changes and additions to look for in upcoming price list publications