Price List Update Summary - February 2026

New Xactimate Line Items

Looking for more accurate and consistent Xactimate estimates? Check out Actionable Profile, a powerful estimating tool that provides live guidance, industry-standard alerts, and built-in macros to help reduce overages, omissions, and common estimating mistakes.

Learn more about Actionable Profile

February 2026 Price List Changes Report

February 2026 Price List Updates Summary

Upcoming Major Additions / Modifications for next month’s 2026 Publication
1: Add items for high grade vinyl cove base molding.
2: Add items for power washing to the PNT (Painting) category.
3: Review Low-E definitions for applicable items in the window categories.
4: Review material associations and definition qualifiers for the snaplock laminate floor series of items.
5: Adding new RFG 300- Standard grade laminated shingle item, including corresponding series of items, for the May publication.
6: Incorporating major brands and product series into the laminated shingle definitions for the new RFG 300- series of items and the RFG 300 series of items for the May publication.
Structural price list items added for the February 2026 price lists
1: CABVENDOR Cabinet Vendor Report/Assessment (Bid Item) (+) (+)
Notes: Cabinet repair assessment following a water or fire event. Bid Item.
2: HMRASBPLA Tear off asbestos plaster (no haul off) (-) (-)
Included: Labor cost to remove asbestos plaster (including lath, if applicable) and to bag for disposal.
Excluded: Asbestos testing, containment barriers (HMR BARR), dump/disposal fees (HMR HWD for hazardous waste disposal), personal protective equipment (HMR PPE*).
Quality: 6 mil bags.
Notes: Debris is double bagged. The labor type used in this item is a hazardous materials remediation technician, who typically performs work relating to hazardous materials, which may include asbestos, lead, mold, etc. Pricing can have a wide variance based on several factors, such as method of removal, condition of plaster, presence and/or type of lath, company's pricing structure, etc. Verisk recommends comparing with specific local costs/bids and making adjustments as necessary.
3: HMRWEP Window exhaust port (+) (+)
Included: Lumber, fasteners, tape, coupling, and labor.
Excluded: Ducting.
Notes: Materials and labor to create an exhaust opening/port for a window when using negative pressure in an area.
4: TMPTARPI Tarp - lift & inspect only - per sq ft (+) (+)
Included: Labor to lift existing tarp, assess/inspect damage, and re-secure existing tarp.
Notes: Item is intended for unfastening and lifting sections of previously installed tarp for assessing and inspecting damage, and for re-securing tarp.
5: TMPTARPSI Tarp w/sandbags - lift & inspect only - per sq ft (+) (+)
Included: Labor to lift existing tarp, assess/inspect damage, and re-secure existing tarp.
Notes: Item is intended for unfastening and lifting sections of previously installed tarp with sandbags for assessing and inspecting damage, and for re-securing tarp.
6: WTRWEP Window exhaust port (+) (+)
Included: Lumber, fasteners, tape, coupling, and labor.
Excluded: Ducting.
Notes: Materials and labor to create an exhaust opening/port for a window when using negative pressure in an area.
Structural price list material components added for the February 2026 price lists
1: BOLT3/8X10C Carriage bolt - 3/8" x 10" - zinc coated
2: BOLTW2/8X2 Fender washer - 3/8" x 2" - zinc coated
3: NUT3/8Z Nut - 3/8" - zinc coated
Structural price list items modified for the February 2026 price list
1: FRMBLK Modified labor component yield in (+) and (-) assemblies.
2: FRMRFO Modified labor component yield in (+) assembly.
3: INSHWRAP* Modified material component yield of house wrap in (+) assembly.
4: MTLPP Modified material component yield of house wrap in (+) assembly.
5: SDGHWRAP* Modified material component yield of house wrap in (+) assembly.
Structural price list material components modified for the February 2026 price lists
1: INSHWRAP Modified unit type from LF to SF.
Miscellaneous changes made for the February 2026 price lists
Modified the New Construction Labor Efficiency labor supporting events for CLN-LAB (from 7.292% to 13.542%), CLNT-LAB (from 12.5% to 17.708%), and CON-LAB (from 5.208% to 13.542%).