Price List Update Summary - July 2026

New Xactimate Line Items

Looking for more helpful Xactimate estimating information? Check out the Commonly Overlooked Line Items database of Xactimate line items that are often warranted but rarely included in invoices/estimates!

COMMONLY OVERLOOKED LINE ITEMS

July 2026 Price List Changes Report

July 2026 Price List Updates Summary

Upcoming Major Additions / Modifications for next month’s 2026 Publication
1: Review cabinet line item assumptions.
2: Review finish flooring items for clarity.
Structural price list items added for the July 2026 price lists
1: ELEIBB Intersystem bonding bridge (+ / -) (+)
Included: Intersystem bonding bridge, grounding lugs, concrete anchors, grounding wire, and installation labor.
Quality: UL-listed, corrosion-resistant metal unit with stainless steel hardware and a weather-resistant protective cover.
(-)
Included: Labor cost to remove an intersystem bonding bridge and to discard in a job-site waste receptacle.
2: ELEMBR Meter mast bracing kit for roof (+ / -) (+)
Included: Meter mast bracing kit, roofing cement, and installation labor.
Quality: Roofing kit may include rigid or guy wire type bracing for up to 3" diameter mast.
(-)
Included: Labor cost to remove mast bracing and to discard in a job-site waste receptacle.
3: EQUSKIDD< Mini skid steer loader (per day) - no operator (+) (+)
Included: Mini skid steer loader.
Quality: Stand-on.
Excluded: Equipment operator.
Notes: Daily charge for equipment.
4: EQUSKIDM< Mini skid steer loader (per month) - no operator (+) (+)
Included: Mini skid steer loader.
Quality: Stand-on.
Excluded: Equipment operator.
Notes: Monthly charge for equipment.
5: EQUSKIDW< Mini skid steer loader (per week) - no operator (+) (+)
Included: Mini skid steer loader.
Quality: Stand-on.
Excluded: Equipment operator.
Notes: Weekly charge for equipment.
6: HVCFRRBL Furnace repair - blower motor (+) (+)
Included: Blower motor and replacement labor.
7: HVCFRRBR Furnace repair - burner (+) (+)
Included: Burner and replacement labor.
Notes: Price based on the replacement of a single burner. Price may need to be adjusted if multiple burners need to be replaced.
8: HVCFRRCB Furnace repair - control board (+) (+)
Included: Control board and replacement labor.
9: HVCFRRFS Furnace repair - flame sensor (+) (+)
Included: Flame sensor and replacement labor.
10: HVCFRRHE Furnace repair - heat exchanger (+) (+)
Included: Heat exchanger and replacement labor.
11: HVCFRRIG Furnace repair - ignitor (+) (+)
Included: Ignitor and replacement labor.
12: HVCFRRLS Furnace repair - limit switch (+) (+)
Included: Limit switch and replacement labor.
13: SPEWVRS Weathervane - Detach & reset (+) (+)
Included: On-site storage and labor.
Excluded: Any additional materials or hardware.
Notes: Labor cost to detach a weathervane, store on site, and reinstall at a later time.
14: WTRACT3N Remove wet ceiling tile & drywall, no bagging - Cat 3 (-) (-)
Included: Labor cost to remove wet, Category 3 water-damaged drywall and attached ceiling tiles, including nails and screws, and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials.
15: WTRACT3NA Remove wet ceiling tile & drywall, no bagging-Cat 3 aft hrs (-) (-)
Included: Labor cost to remove wet, Category 3 water-damaged drywall and attached ceiling tiles, including nails and screws, and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials and for working after normal business hours.
16: WTRACTASN Remove wet ceiling tile w/staples, no bagging (-) (-)
Included: Labor cost to remove wet ceiling tiles attached with staples to furring strips (includes removal of the staples) and to discard in a job-site receptacle.
Excluded: Bagging.
17: WTRACTASNA Remove wet ceiling tile w/staples, no bagging - after hours (-) (-)
Included: Labor cost to remove wet ceiling tiles attached with staples to furring strips (includes removal of the staples) and to discard in a job-site receptacle.
Excluded: Bagging.
Notes: A premium charge is used after normal business hours.
18: WTRACTN Remove wet ceiling tile & drywall, no bagging (-) (-)
Included: Labor cost to remove drywall and attached ceiling tiles, including nails and screws, and to discard in a job-site receptacle.
Excluded: Bagging.
19: WTRACTNA Remove wet ceiling tile & drywall, no bagging - after hours (-) (-)
Included: Labor cost to remove drywall and attached ceiling tiles, including nails and screws, and to discard in a job-site receptacle.
Excluded: Bagging.
Notes: A premium charge is used after normal business hours.
20: WTRACTS3N Remove wet ceiling tile w/staples, no bagging - Cat 3 (-) (-)
Included: Labor cost to remove wet, Category 3 water-damaged ceiling tiles attached with staples to furring strips (includes removal of the staples) and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials.
21: WTRACTS3NA Remove wet ceiling tile w/staples, no bag - Cat 3 after hrs (-) (-)
Included: Labor cost to remove wet, Category 3 water-damaged ceiling tiles attached with staples to furring strips (includes removal of the staples) and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials and for working after normal business hours.
22: WTRACTSN Remove wet suspended ceiling tile, no bagging (-) (-)
Included: Labor cost to remove suspended acoustical ceiling tile and to discard in a job-site receptacle.
Excluded: Bagging.
23: WTRACTSNA Remove wet susp. ceiling tile, no bagging - after hours (-) (-)
Included: Labor cost to remove suspended acoustical ceiling tile and to discard in a job-site receptacle.
Excluded: Bagging.
Notes: A premium charge is used after normal business hours.
24: WTRACTSSN Remove wet suspended ceiling tile, no bagging - Cat 3 (-) (-)
Included: Labor cost to remove wet, Category 3-damaged suspended acoustical ceiling tile and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials.
25: WTRACTSSNA Remove wet suspended ceiling tile, no bag - Cat 3 after hrs (-) (-)
Included: Labor cost to remove wet, Category 3-damaged suspended acoustical ceiling tile and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used for working with sewage contaminated materials and for working after normal business hours.
26: WTRTACKN Tear out tackless strip, no bagging (-) (-)
Included: Labor cost to remove tackless strip and to discard in a job-site waste receptacle.
Excluded: Bagging.
27: WTRTACKNA Tear out tackless strip, no bagging - after hours (-) (-)
Included: Labor cost to remove tackless strip and to discard in a job-site waste receptacle.
Excluded: Bagging.
Notes: A premium charge is used after normal business hours.
Canada only structural price list items added for the July 2026 price lists
1: FRMULD Underlayment - dimple - 5/32" - 1/4" overall thickness (+ / -) (+)
Included: Underlayment, seam tape, and labour to install.
Quality: 5/32" to 1/4" dimple underlayment; installed for moisture barrier and/or mold reduction membrane.
Notes: This item should be used when the underlayment is being installed during the framing or finish carpentry phase.
(-)
Included: Labour cost to remove underlayment and to discard in a job-site waste receptacle.
2: FRMULD> Underlayment - dimple - over 1/4" overall thickness (+ / -) (+)
Included: Underlayment, seam tape, and labour to install.
Quality: Over 1/4" thick dimple underlayment; installed for moisture barrier and/or mold reduction membrane.
Notes: This item should be used when the underlayment is being installed during the framing or finish carpentry phase.
(-)
Included: Labour cost to remove underlayment and to discard in a job-site waste receptacle.
Structural equipment components added for the July 2026 price lists
1: SKIDSTEER< Mini skid steer loader
2: SKIDSTEERM< Mini skid steer loader (per month)
3: SKIDSTEERW< Mini skid steer loader (per week)
Structural material components added for the July 2026 price lists
1: ELEIBB Intersystem bonding bridge
2: ELEMBR Meter mast bracing kit for roof
Structural price list items modified for the July 2026 price list
1: ELSSOLARP Modified Quality field of (+) definition to reference range in wattage.
2: ELSSOLARP> Modified Quality field of (+) definition to reference range in wattage.
3: LABSUPERR Modified Note field of (+) definition to clarify a typical single-family detached rebuild or new build generally requires significantly fewer hours per weekday, while larger multi-family or multi-unit projects may warrant full-time formal supervision.
4: RFGBRCFRS Modified description, (+) assembly, and (+) definition to include electrical mast roof bracing kits and assumptions for roofing cement.
5: RFGSTEP* Added default calculation.
6: SFGDICE* Added text to Note field of (+) definition to clarify intent of line item.
7: SPEWV* Added ( R ) activity.
8: WTRCB Modified description, labor component yield, and Excluded definition to clarify item is for tearing out material "up to Category 3" and excludes bagging.
9: WTRCBA Modified description, labor component yield, and Excluded definition to clarify item is for tearing out material "up to Category 3" and excludes bagging.
10: WTRCBB* Modified labor component yield in (-) assembly.
11: WTRTACK Modified labor component yield in (-) assembly.
12: WTRTACKA Modified labor component yield in (-) assembly.
13: WTRTACKSN* Modified labor component yield in (-) assembly.
Structural price list material components modified for the July 2026 price lists
1: ELSSLRP< Modified description to reference range in wattage.
2: ELSSLRP> Modified description to reference range in wattage.
Miscellaneous changes made for the July 2026 price lists
1: Added descriptive text to Note field of the (+) definitions of various items within the following Personal Property Item categories: CMP, HSW, LGP, OFS, SPG, and TOL.